HomeMy WebLinkAboutAgenda Packet - EVWD Board of Directors - 07/19/2018SPEC IA L BO A RD MEET IN G
J uly 19, 2018 at 5:30 PM
31111 Greenspot Road
Highland, C A 92346
AGE N D A
C A LL TO O RD ER
PLED G E O F A LLEG IA N C E
RO LL C A LL O F BO A RD MEMBERS
PUBLIC C O MMEN T S
Any person wishing to speak to the Board of Directors is asked to complete a Speaker
Card and submit it to the D istrict C lerk prior to the start of the meeting. Each speaker is
limited to three (3) minutes, unless waived by the Chairman of the Board. Under the State
of C alifornia Brown Act, the Board of Directors is prohibited from discussing or taking
action on any item not listed on the posted agenda. T he matter will automatically be
referred to staff for an appropriate response or action and may appear on the agenda at a
future meeting.
1.Design-Build Training
REPO RT S
2.General Manager/C EO
3.Legal C ounsel Report
4.Board of Directors' C omments
A D J O URN
P urs uant to G overnment C o d e S ec tio n 54954.2(a), any reques t for a d is ab ility-related modific ation or
ac commodation, inc luding auxiliary aid s o r s ervic es , that is s o ught in order to p artic ip ate in the above
agendized public meeting should be direc ted to the District C lerk at (909) 885-4900.
July 19, 2018
Progressive Design Build
Ash Dhingra P.E.,S.E
“TRADITIONAL PROCUREMENT”
Design-Bid-Build (DBB)
•Design to 100%, procurement (bid), and
construction proceed sequentially
•Construction contract awarded to lowest
bidder based on completed plans and
specifications
Designer and Contractor are two separate entities
Owner holds separate contracts with each
Owner
Designer Contractor
Subcontractors
DRAWBACKS OF TRADITIONAL DELIVERY
•Owner holds all contracts –Owner in the middle of all disputes
•Low bid can lead to contentious environment or low quality
•Harder to attract qualified bidders in tight construction market
“ALTERNATIVE” DELIVERY
•Also known as integrated project
delivery
•Design-Build (DB)
•Design-Builder is both engineer and
general contractor
•Typically design to 60% and begin
construction
•Contract pricing is set very early in project
Owner holds single contract with one entity responsible for design and construction
Designer and Contractor are one contractual entity
Owner
Design-Builder
Subcontractors
WHY DESIGN-BUILD?
•Single point of responsibility
•Eliminates conflict between designer and contractor
•DB entity responsible for performance guarantees
•Simpler and shorter best value procurement process
•Encourages innovation in design and construction
•Control of final construction cost, known upfront
OWNER GETS OUT OF THE MIDDLE
One Entity Guarantees Cost Savings
•Price
•Schedule
•Quality
•Performance
•Benefits of true integration
•Less design
•Less construction
administration
MULTIPLE VARIATIONS OF DESIGN/BUILD
Design Build
Lump Sum/ Bid 2 Step/ Phased/ GMP/ Progressive
COMPARING SEQUENCE OF A DBB VS DB PROJECT
DBB Design Bid & Award Construction
Construction Bid Price Unknown Until full design completion and Bid
DB Pre-Design & Procurement Design
Construction (begins as soon as GMP Fixed)
Guaranteed Maximum Price (GMP) Fixed Earlyduring early design development
True Construction Cost Unknown until change orders done and warranty issues resolved
KEY FEATURES -PROGRESSIVE DESIGN BUILD
•Planned early communication of schedule and budget restraints
•Design to Price approach –set a firm budget for GMP.
•“Off -Ramp” available to change to Design-Bid-Build
•3rd party Owner’s Advisor
ROLE OF A PROGRAM MANAGER
•Impartial Expert
•Technical Advisor
•Complete Project
Overview
TWO STEP SELECTION PROCESS
•In accordance with Assembly Bill 642
•RFQ
•RFP
•Selection Criteria
•Best Value
•Refinement of Scope of Work
•Best and Final Offer
SELECTION PROCESS FOR BEST DESIGN-BUILDER
STEP 1 STEP 2
Release Request for Qualifications Release Request for Proposals
Receive Statement of Qualifications
(SOQ)
Receive Proposals
Review and Evaluate SOQ’s Review and Evaluate Proposals
Interview Design-Builder Interview Design Builders
Shortlist Design=Builders to Receive
Request for Proposals
Select Design Builder and
Recommend for Contract Award
Progressive Design-Build (PDB)
•PDB relies on a collaboration between the Owner and Design-Builder with constant communications
•Risks associated with the project are defined, assigned and controlled by the party having most control on that risk, some may be mutually shared
•A Risk register is created for the project
•Design-Builder bids project in packages to subcontractors or by trade and similarly bids for equipment from suppliers
Owner
Design/Builder
Subcontractors
ADVANTAGES OF PROGRESSIVE DESIGN-BUILD
•Simple and inexpensive procurement process can be
completed in a short timeframe
•Project can be implemented in phases or task orders to save
time or keep the project moving
•Maximizes owner flexibility, involvement and control of the
project
PROGRESSIVE DESIGN-BUILD
BENEFITS TO OWNER OTHER CONSIDERATIONS
•Allows more effective owner input into
the scope, features, and operational
aspects of the design.
•Shorter procurement process.
•Potential for more bids.
•Flexibility to complete work design to
budget based on (available funding).
•Better chance of adhering designing to
budget.
•Cost and schedule for construction are
not fixed at the time of initial contract
signing.
•Procurement of long-lead equipment
will be delayed until GMP agreement.
PDB EXPEDITES SCHEDULE
How does it happen?
•Early equipment selection
•Designing around specifics
•Early work packages
•Procuring while designing
•Integrated team (design,
construction and operations)
•Reduced conflicts and
interferences
•Early stakeholder
involvement
•Owning the schedule
DESIGN BUILDER BIDS PACKAGES
•Clear & Grubbing and Mass
Grading of Site
•Long lead equipment packages
•Pipelines
•Concrete and Rebar
•Mechanical and equipment
•Electrical and Instrumentation
& Controls
•Civil and Sitework, fencing etc.
•Buildings
•Landscaping
•Other Specialty Work
WHAT’S IN A GUARANTEED MAXIMUM PRICE(GMP)?
GMP is open book completely accessible to Owner
Design Engineering Services to develop design to 60% level to develop a GMP Phase I
Design Engineering Services to complete design to 100% and Engineering Services during construction
Subcontracted work and equipment packages including long lead time items
Project and Construction Management & Supervision, QC
General Conditions based on construction duration
Contingency & escalation to mid point of construction
GUARANTEED MAXIMUM PRICE DELIVERY METHOD
Savings
Allocation
Cost
Overruns
Overruns
Allocation
Cost Savings
While the owner keeps
most of the savings, a
portion is reserved for
the design-build team
as an incentive.
If the DB actors share
the overruns, an upper
limit normally exists for
the A/E’s cost liability.
Constructor
e.g. 90%
A/E
e.g. 10%
Owner
Constructor
Architect/Engineer
SUMMARY
•Progressive Design-Build was recommended
•Single point of responsibility
•Promotes greatest level of innovation with the schedule
benefits of design-build
•Greater staff involvement in process and equipment
selection as well as operational controls
•Control of budget and collaboration to achieve best value
RECENT WATER DESIGN BUILD COUNCIL
MARKET STUDY
•The median schedule growth after contract award for DB projects is half as large as the schedule growth for DBB projects
•DB projects finish on or below contract price twice as often as DBB projects
•Contracts using guaranteed maximum prices (GMPs) are more likely to have no schedule or cost growth as compared to projects with lump-sum contracts
•There is no significant difference in constructed quality between design-build and design-bid-build projects
For more information:
www.waterdesignbuild.org