HomeMy WebLinkAboutAgenda Packet - North Fork Water Company - 04/07/2015NORTH FORK WATER COMPANY
ANNUAL SHAREHOLDERS MEETING
April 7, 2015
Financial Statements & Report
•Annual Financial Report
–Review company’s financial position and results of
operations
–Instrument of financial disclosure
•Independent Accountant’s Review
–No Findings
EXECUTIVE SUMMARY OF FINANCIAL STATEMENTS
Assets
Cash $ 160,494
Cash – Restricted for Capital Projects 59,804
Fixed Assets/Water Rights 3,047,177
Other Assets 21,100
Total Assets $ 3,288,575
Liabilities $ 69,927
Shareholder Equity 3,218,648
Total Liabilities & Equity $ 3,288,575
2014-15 Expenses
Repairs & Maintenance $ 47,112
Property Taxes 29,411
Other General & Administrative 44,989
Depreciation 54,838
$ 176,276
2014-15 Assessments $ 193,212
Change in Shareholder Equity $ 16,936
Operating Budget To Actual
Budget Actual
Water Purchases - -
Operating Labor $ 39,000 $ 39,061
Contract Services 27,100 39,715
Materials & Supplies 230 29
Administration 10,245 7,633
Insurance 4,050 4,863
Property , Franchise Taxes 39,000 29,411
Depreciation - -
$ 119,625 $ 120,712
2014-15 Assessments ($17) $ 121,652 $ 121,652
Increase in Operating Reserve $ 2,027 $ 940
Replacement Reserve Budget To Actual
Budget Actual
Pipeline Replacement - SAR $ 60,000 $ 34,333
Weir 17 Gate Replacement - 1,310
$ 60,000 $ 35,643
2014-15 Assessments ($10) $ 71,560 $ 71,560
Increase in Replacement Reserve $ 11,560 $ 35,917
Beginning Reserve Balance $23,887
Ending Reserve Balance $ 59,804
Operational Challenges
–Drought
•Low water levels in Santa Ana River for
deliveries during non-contract months
•Limited water availability for Bear Valley
Mutual to meet obligations during contract
months
–Infrastructure
•Exposed pipes deteriorating due to age and
vandalism
•Limited replacement funding
Operations and Maintenance
•Operations
–Monthly deliveries to 17 shareholders through 13 weirs
–Total 2014-15 water available: 142,861 minors inches
•94,650 from BV contract
•48,211 from SAR flows
–Total 2014-15 Deliveries
•131,640 minors inches
•To EVWD were 113,745 minors inches ( 79.6%)
•Maintenance
–Monthly weed/brush control
–Preliminary survey work
Capital Expenditures
•Capital Expenditures - Completed
–Replace leaking pipe from SAR crossing to NF
intake
–Replace broken slide gate with gate valve (weir 17)
•Capital Expenditures - Proposed
–Engineering study, replacement of SAR crossing and
Plunge Creek siphon – Estimated Cost $30,000
–Complete survey and marking of North Fork
pipeline alignment – Estimated Cost $16,000
Old pipe that has
never been replaced
Significant water leak
supports tree growth,
which threaten pipe
Pipeline Crossing the Santa Ana River
Repair band stolen
exposing weak welds
Pipes being dented
by thrown rocks
Plunge Creek Siphon
Water Deliveries
Rights Under 1885 Contract Terms
MONTH ALLOTMENT
(MINER’S INCHES PER
DAY)
ALLOTMENT
PER SHARE
(MINORS INCHES)
FEBRUARY TO MAY 25% OF SANTA ANA
RIVER FLOW
JUNE 500 2.1
JULY 600 2.6
AUGUST 600 2.6
SEPTEMBER 550 2.3
OCTOBER 450 1.9
NOVEMBER 400 1.7
DECEMBER & JANUARY 25% OF SANTA ANA
RIVER FLOW
2015-16 Projected Water Deliveries
MONTH
ESTIMATED
ALLOTMENTS
(MID)
ESTIMATED
ALLOTMENTS
PER SHARE(MI)
WITH
SUPPLEMENTAL
WATER (MID)
February 219 .8 .8
March 238 .9 .9
April 230 .9 2.3
May 230 .9 2.3
June 500 2.1 2.1
July 600 2.6 2.6
August 600 2.6 2.6
September 550 2.3 2.3
October 450 1.9 1.9
November 400 1.7 1.7
December 186 .7 2.1
January 186 .7 .7
DESCRIPTION ADOPTED 2014-15
BUDGET
PROPOSED 2015-16
BUDGET
Operating Expenses
Water Purchases (1,190 AF of SWP) $ 0 $ 150,000
Operating Labor /Equipment- EVWD 39,070 53,400
Contract Services 27,100 25,000
Legal Services 0 30,000
Materials & Supplies 230 1,000
Administration 10,000 10,000
Director Fees 175 100
Insurance 4,050 4,100
Property Taxes 39,000 30,000
Total Operating Expenses $119,625 $303,600
Capital Expenditures $60,000 $46,000
PROPOSED 2015-16 BUDGET
DESCRIPTION PROPOSED 2014-15 BUDGET
Proposed Funding
Operating Expenses - Other $ 153,600
Operating Expenses – Water Purchases 150,000
Replacement Expenditures 46,000
Replacement Reserve Contribution 25,560
Total Proposed Funding:$ 375,160
Proposed Assessments – 7,156 Shares
Operating Assessment - Other $22 per share
Operating Assessment-Water Purchases (Optional) $21 per share
Replacement Expenditures & Reserve (Optional) $10 per share
Total Assessment: $53 per share
2015-16 ASSESSMENTS
QUESTIONS?