HomeMy WebLinkAboutAgenda Packet - EVWD Board of Directors - 06/02/2008EastValley
~, `~Nater District
SPECIAL MEETING
JUNE 2; 2008 - 8:30 a.m.
EAST VALLEY WATER DISTRICT
3654 HIGHLAND AVE #12, HIGHLAND, CA.
AGENDA
CALL 70 ORDER
PLEDGE OF ALLEGIANCE
1. Public Comments
~:. Discussion and possible action regarding the District Headquarters
design and update.
~4. ADJOURN
Pursuant to Government Code Section 54954.2(a), any request for adisability-related
modification or accommodation, including auxiliary aids or services, that is sought in order to
participate in the above agendized public meeting should be directed to the District's
Administrative Manager at (909) 885-4900 at least 72 hours prior to said meeting.
1Vlemorandum
To: Bob Martin, General Manager /
From: Ron Buchwald, District Engineer Qg ~~~08
Date: 5/6/08
Re: Headquarter Building Review by District Staff
As requested by the Board, deparhnent heads and supervisors met to review the Headquarter
Buildings to determine areas where various items could be removed, delayed or changed to
reduce the cost of construction. The meeting was held on February 15, 2008. The group
met as a whole and reviewed the plans in an open forum. The following items listed would
not need to have the building plans resubmitted to the City for additional review (these
changes were internal and did not effect the building structure themselves):
1) Downsize /Delay /Delete the building of the Garden Exhibit. The City of
Highland has a small conservation garden exhibit less than 2 miles away at the
new City Library.
2) Delete the gym and locker rooms in the main building. This area could be
converted to office space for the remaining production staff in lieu of expanding
the building at Plant 150 to include the office space needed for them.
3) Delay /Delete the furnishing of the break room in the Field Building adjacent to
the main building, which has a good sized break room already.
4) Delete the installation of the large vehicle lift in the garage. Currently, work on
the large vehicles is normally sent to outside repair facilities. In addition, instead
of building the remaining lifts below ground, replace them with above ground
lifts (which are generally cheaper to install and replace).
5) Delay /Delete the furnishing of the shower and locker room in the garage. The
Field building has an extensive shower and locker room for this purpose.
6) Delay /Delete the pipe rack adjacent to the Warehouse building used to store
pipe on a temporary basis. All pipe to be delivered to the construction site or
Plant 39.
The above items were thought to be minimal cost savings to the overall construction cost
maybe in the $500,000 to $1 million range. For significant cost savings, staff thought of
some additional items that would most likely need significant plan changes and a re-
submittal to the City for additional review. This would require additional cost for the
redesign of the plans and plan checking and more significantly, additional time to acquire
the permits.
May 6, 2008
7) Consider redesigning the garage to a single story instead of the current two-story
building. Again, large vehicles are usually sent to outside repair facilities and the
need of a large vehicle lift and atwo-story building is not needed.
8) Downsize /Delay /Delete the water features in and around the main building.
9) Remove the Weld shop and Pipe Fabrication shop from the Field Operations
building. Keep as an open area and delete the exterior walls and large doors.
10) Delete the Field Operations building and move staff to the Warehouse building
by down sizing the storage area. Not all deparhnent heads and supervisors were
in agreement with this idea.
One item of note that was discussed during the meeting with staff is that the layout and
design of the new headquarters was performed with an eye to the future, near ultimate build
out of the District. The larger than required garage is a perfect example of this where the
thought was at some point in the future the District may consider performing all repair work
with District staff only. The garage was designed with this in mind (large vehicle lift and
two-story building). A larger than needed main building, field office and warehouse was
also designed with that in mind. In some cases, the District has utilized some of the future
space due to growth that has occurred since the design of the buildings, which was over f ve
years ago. )n other words, some of the extra office space designed for future growth will be
used once the building is completed (hence the need for Suite 19).
There are, of course, other ideas that can save various amounts in construction cost but the
items above were what came to mind and mostly agreed upon by staff. If there are other
ideas, please do not hesitate to forward them to us for additional review and comment, if
you so desire.